Project
Construction of a new 43,000-seat baseball stadium in South Philadelphia.
The project was performed under the direction of a construction manager
using multiple subcontract agreements for the major work disciplines.
Stadium construction was from April 2002 to April 2004.
Services
Buric developed the initial resource-loaded CPM schedules
for the mechanical contractor and the plumbing contractor. The schedule
was formatted and established cross-compatible to the construction manager’s
and owner’s master schedules. Buric assisted the contractor
with schedule impact analysis and documentation of issues.